When does a negative cost variance (CV) occur in earned value management?
When the actual cost is more than the earned value.
A negative cost variance (CV) occurs when the actual costs incurred for a project exceed the value of the work that has been completed, indicating that the project is over budget.
This choice does not define a negative cost variance. Cost variance being greater than schedule variance simply compares two types of variances but does not indicate whether costs are under or over budget. It does not provide information about the relationship between actual costs and earned value.
In this scenario, a positive cost variance results since the project is under budget. When earned value exceeds actual cost, it indicates that the project is progressing well financially, contrary to the definition of a negative cost variance.
This statement accurately describes a negative cost variance. When actual costs surpass the earned value, it signifies that more money has been spent than what is justified by the work completed, resulting in a negative cost variance.
Similar to option A, this choice merely compares two types of variances without establishing the actual relationship between costs and earned value. It does not provide sufficient information to conclude whether the project is over or under budget.
A negative cost variance in earned value management specifically arises when actual costs exceed earned value, indicating budget overruns. Understanding this concept is crucial for project managers to assess financial performance and take corrective measures when necessary. The other options either define different scenarios or focus on comparisons that do not address the core definition of negative cost variance.
Related Questions
View allA project is running ahead of schedule. The project manager decides to...
A local government notices that a 10-foot deep sinkhole appeared in th...
Canton Technologies is about to sign a three-year contract with a larg...
Due to an error in the change approval and tracking system, a revision...
A team of software developers working on an IT project has two lines o...
Related Quizzes
View all0PC1 Planning Instructional Strategies for Meaningful Learning Version 1
AP01 Elementary Literacy Curriculum Version 1
AQ01 Applied Healthcare Statistics C784 Version 1
ASO1 Introduction to Statistics for Research Version 1
BJ01 Introduction to Business Finance Version 1
C172 Network and Security Foundations Version 1
C180 Introduction to Psychology Version 1
C180 Introduction to Psychology Version 2
CKC1 Introduction to Humanities Version 1
DZ01 Mathematics for Elementary Educators III MATH 1330 Version 1
- ✓ 500+ Practice Questions
- ✓ Detailed Explanations
- ✓ Progress Analytics
- ✓ Exam Simulations