During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed.What should the project manager do?
Review the requirements traceability matrix with the concerned stakeholder.
The requirements traceability matrix (RTM) is a valuable tool that links requirements to their source and helps verify that all requirements are being addressed throughout the project. By reviewing the RTM with the stakeholder, the project manager can ensure clarity on which requirements have been fulfilled and address any concerns regarding missing deliverables.
While checking the approved list of requirements is a reasonable step, it does not directly address the stakeholder's concern. This action may reveal missing items, but without stakeholder input, it lacks the collaborative aspect needed to resolve the issue effectively.
This option implies that new requirements may need to be added without first confirming the stakeholder's concerns regarding the existing requirements. This could lead to unnecessary changes and does not address the immediate need to clarify existing deliverables.
Improving the acceptance criteria may be beneficial, but it doesn't directly resolve the concern about whether a specific requirement is being addressed. The focus should first be on reviewing current requirements rather than modifying criteria without confirming existing deliverables.
The most effective approach for the project manager is to review the requirements traceability matrix with the concerned stakeholder. This collaborative review will clarify any misunderstandings about the requirements and ensure that all concerns are properly addressed, thereby reinforcing stakeholder confidence in the project's deliverables.
Related Questions
View allAn agile project is running activities to define the minimum viable pr...
A project team member, who is inexperienced in system development work...
A project manager meets with external stakeholders to explain the obje...
A project manager just completed a successful deployment and is prepar...
A product owner presented the backlog to the team, and the team raised...
Related Quizzes
View all- ✓ 500+ Practice Questions
- ✓ Detailed Explanations
- ✓ Progress Analytics
- ✓ Exam Simulations