A new project manager was assigned to a project during implementation. The project manager realized that new tax policies are creating a risk for a cost overrun by 25%. The project manager updated the risk register and kept the project running as normal. The CEO has announced that the project could be cancelled since the acceptable cost overrun is only 20%. The project manager was quite surprised as this was new information. What should the project manager have done to avoid this?
Implemented the communications management plan properly.
Effective communication with stakeholders is crucial for a project manager to ensure that all parties are aware of project risks and any changes that could impact project viability. In this scenario, the project manager's failure to communicate new tax policies and their potential impact on project costs led to unexpected decisions from the CEO regarding project cancellation.
While engaging stakeholders is important, it does not directly address the need for timely and effective communication of risks. The project manager may have engaged stakeholders, but without proper communication about the new tax policies and their implications, stakeholders, including the CEO, remained uninformed about critical project risks.
Although providing a risk response is essential, the project manager first needed to communicate the risk effectively to stakeholders. Without informing the CEO and other key stakeholders about the 25% cost overrun risk, the project manager could not implement an appropriate risk response or mitigation strategy.
Updating the risk tolerance is important; however, it is not a substitute for ensuring that all stakeholders are aware of the current project risks. The project manager's lack of communication meant that the CEO was unaware of the potential for cost overruns, leading to a misalignment in expectations regarding acceptable risk levels.
In project management, clear and timely communication is essential to keep all stakeholders informed about risks and changes that may affect the project's outcome. The project manager's oversight in implementing the communications management plan hindered their ability to relay crucial information regarding the new tax policies and associated risks, ultimately resulting in a situation where the CEO was caught off guard by the risk of a cost overrun. Proper communication could have enabled proactive discussions and decisions about the project's future.
Related Questions
View allThe project manager started a new project and must ensure that the tea...
As a member of an organizational change management team, a project man...
An agile project is running activities to define the minimum viable pr...
During the implementation of a project, the project team discovered a...
A project sponsor commonly asks the project manager to skip project re...
Related Quizzes
View all- ✓ 500+ Practice Questions
- ✓ Detailed Explanations
- ✓ Progress Analytics
- ✓ Exam Simulations