Difficulty: Easy
Average Score: 77%
A project team is working on obtaining offices to another building and providing new furniture. The new furniture was purchased from an international wreck currency, and size to changes in the exchange rate. the cost has increased by 10%. There is no contingency in the project budget.

What should the project manager do?