What is the equation to calculate cost variance (CV)?
CV = EV - AC
Cost Variance (CV) is calculated by subtracting Actual Cost (AC) from Earned Value (EV). This equation helps project managers determine whether they are under or over budget at a given point in the project.
This equation suggests dividing Earned Value (EV) by Budget at Completion (BAC), which is incorrect. CV is concerned with the difference between what has been earned and what has been spent, rather than a ratio of these values, making this formula irrelevant for cost variance calculations.
This option indicates subtracting Budget at Completion (BAC) from Earned Value (EV), which does not reflect actual costs incurred. CV specifically compares earned value to actual costs (AC), not the budgeted amount, and thus this formula does not provide a valid assessment of cost performance.
This choice presents a ratio of Earned Value (EV) to Actual Cost (AC), which does not yield a variance but rather a cost performance index. While useful for understanding efficiency, this calculation does not determine the difference between what was earned and what was spent, which is essential for calculating CV.
This equation correctly identifies Cost Variance (CV) as the difference between Earned Value (EV) and Actual Cost (AC). This formula allows project managers to see if they are spending less than (positive CV) or more than (negative CV) what they have earned for the work performed.
Cost Variance (CV) is essential for project management as it highlights financial performance relative to budgeted and actual expenditures. The correct formula, CV = EV - AC, provides insight into whether a project is under or over budget, while the other options either misrepresent the relationship between these values or focus on ratios rather than variances. Understanding this concept allows for better financial control and project adjustments as needed.
Related Questions
View allIn one of the project meetings during a project execution, a new stake...
Which response would be the most appropriate?
Which method should be used to elicit a cross-functional requirement
A Scrum team has a product backlog and a sprint backlog. Which of the...
Which two of the following items should be included in the planning? (...
Related Quizzes
View all- ✓ 500+ Practice Questions
- ✓ Detailed Explanations
- ✓ Progress Analytics
- ✓ Exam Simulations