In a marine construction project, the project manager is informed by the marine authority that the work permit will not be issued until certain environmental reinforcement work has been completed. After reviewing the project management plan, the reinforcement work is not included in the project scope.What should the project manager do?
Start the organization's change control process via a change request.
The project manager must initiate the change control process because the reinforcement work is critical for obtaining the work permit, which is not currently included in the project scope. This ensures that the necessary adjustments are formally documented and approved before proceeding.
While checking with an officer may provide insights about the necessity of the reinforcement work, it does not address the immediate need to adjust the project scope or manage the permit issue. This action is more exploratory and does not lead to the required formal change in the project plan.
Organizing a team meeting and updating the WBS may be beneficial for planning, but without an official change request, these actions lack the necessary authority. The project manager needs to follow the formal change control process to ensure that any modifications to the project scope are recognized and approved by stakeholders.
Although raising the issue is important for awareness, merely updating the progress report does not take the required steps to implement any changes to the project scope. The project manager must actively initiate the change control process to ensure compliance with the marine authority's requirements.
In this scenario, the project manager must start the change control process through a change request to formally include the environmental reinforcement work in the project scope. This approach ensures that all necessary adjustments are documented and approved, allowing the project to proceed in compliance with regulatory requirements. Other options may offer preliminary actions but fail to establish the necessary formalities to address the scope alteration effectively.
Related Questions
View allA project manager created a contingency plan associated with a risk. T...
A project manager is managing a government project that targets the de...
A project manager is leading a project that is in an advanced stage. A...
A project manager is leading a large public project that will have a h...
During the course of a project, the project manager wants to ensure th...
Related Quizzes
View all- ✓ 500+ Practice Questions
- ✓ Detailed Explanations
- ✓ Progress Analytics
- ✓ Exam Simulations