A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects start going to market, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints. This request does not match the project manager's expectation, since a program manager is overseeing the remaining work. How should the project manager approach the situation?