A network architect of a stock exchange broker is implementing a DR, high-availability plan. Which of the following approaches would be the best fit?
Active-active is the best fit for a disaster recovery, high-availability plan.
An active-active configuration allows multiple data centers to be fully operational and share the workload, ensuring that if one site goes down, the other can seamlessly take over without any downtime. This approach provides the highest level of availability and redundancy, which is crucial for a stock exchange broker's operations.
A warm site is a backup facility that is partially equipped and can be made operational within a few hours or days after a disaster. However, it does not provide continuous availability like an active-active setup. The downtime associated with transitioning to a warm site is not suitable for the high-availability requirements of a stock exchange broker.
Active-active setups run multiple data centers concurrently, distributing the workload and providing immediate failover capabilities. This configuration ensures that all sites are fully operational at all times, offering the best solution for high availability as required by the stock exchange broker’s disaster recovery plan.
A full mesh topology refers to a network design where every node is directly connected to every other node, facilitating efficient data routing. While it enhances network reliability, it does not inherently provide disaster recovery or high availability features. Thus, it is not the best approach for implementing a DR plan.
In-band communication involves managing data traffic through the same channel used for regular operations. While it can facilitate system management, it does not address the need for disaster recovery or high availability. This approach could lead to potential data loss or downtime during a failure, making it unsuitable for the broker's needs.
For a stock exchange broker, an active-active configuration is the ideal choice for a disaster recovery and high-availability plan, as it ensures continuous operation and instantaneous failover. Other options, such as warm sites, full mesh topologies, and in-band communication, do not provide the same level of redundancy and reliability required in the critical financial sector. Active-active setups effectively mitigate risks associated with downtime, preserving business continuity.
Related Questions
View allWhich of the following is most closely associated with having a leased...
A company's network is experiencing high levels of suspicious network...
A user's home mesh wireless network is experiencing latency issues. Th...
Users are reporting latency on the network. The network engineer notes...
Which of the following is the best way to keep devices on during a los...
Related Quizzes
View allCompTIA A Plus Certification Exam
CompTIA A Plus Exam Questions
CompTIA A Plus 1001 Exams Practice
CompTIA A Plus Practice Exam
CompTIA CySA+ Cybersecurity Analyst Certification all in One Exam Guide
CompTIA Security Plus Exam Answers
Free CompTIA Security Plus Practice Test
CompTIA Security Plus Simulation Questions
CompTIA Security Plus 501 Practice Questions
CompTIA Security Plus Example Questions
- ✓ 500+ Practice Questions
- ✓ Detailed Explanations
- ✓ Progress Analytics
- ✓ Exam Simulations